Opening Frederick Brooks' The Mythical Man-Month
Frederick Brooks' The Mythical Man-Month
- Length
- 45 min
- Level
- Undergraduate
- Recorded
- Google Research & TechTalks2015 · Public Lecture
Chapter 1 of 7: Before the lecture
Counts the communication channels in a growing team to show why adding staff makes a late project later.
The Mythical Man-Month rests on one claim: people and months are not interchangeable units of effort on a software project. Brooks draws on the OS/360 project to show how added labor brings training overhead and communication bottlenecks. He separates partitionable tasks from those that cannot be divided or compressed, then derives the growth of team interactions from the formula . Chronic optimism and punitive cultures that suppress bad news are traced as causes of failed estimates. The remedies are honest estimates, refusal of impossible deadlines and scope reduction, and the material assumes only general familiarity with professional work.

Your comment is kept while you sign up.Sign in
The Mythical Man-Month rests on one claim: people and months are not interchangeable units of effort on a software project. Brooks draws on the OS/360 project to show how added labor brings training overhead and communication bottlenecks. He separates partitionable tasks from those that cannot be divided or compressed, then derives the growth of team interactions from the formula . Chronic optimism and punitive cultures that suppress bad news are traced as causes of failed estimates. The remedies are honest estimates, refusal of impossible deadlines and scope reduction, and the material assumes only general familiarity with professional work.
The Mythical Man-Month: Essays on Software Engineering
The Art of Computer Programming
Computer Lib
Handbook of Mathematical Formulas and Integrals
Time magazine
The Mythical Man-Month